水电改造验收编制人:__________________
审核人:__________________
审批人:__________________
编制单位:__________________
编制时间:____年____月____日
序言
下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大家解决实际问题。文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!
并且,本店铺为大家提供各种类型的经典范文,如演讲致辞、总结报告、心得体会、合同协议、条据文书、策划方案、导游词、教学资料、作文大全、其他范文等等,想了解不同范文格式和写法,敬请关注!
Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!
Moreover, our store provides various types of classic sample essays for everyone, such as speeches, summary reports, insights, contract agreements, documentary evidence, planning plans, tour guides, teaching materials, complete essays, and other sample essays. If you want to learn about different formats and writing methods of sample essays, please stay tuned!
装饰装修工程竣工验收报告
装饰装修工程竣工验收报告(精选5篇)
我能问一下,什么才是成功吗?“你能用一种旁观者的态度来看待失败,这就是你的成功。”"杏花村。这里给大家分享一下关于装饰装修工程竣工验收报告,方便大家学习。
装饰装修工程竣工验收报告篇1
一、工程完成情况:
__水库除险加固工程经省、市主管部门批准立项,核定总投资1006万元,其中:国债资金投资700万元,地方配套资金306万元。该水库除险加固的主要内容为:
①、大坝前坝坡1563高程以上改为浆砌块石,加固上游坝坡,在大坝左坝肩心墙与溢洪道右侧墙接触面的齿墙后增设一道砼防渗墙;
②、加固溢洪道及下游河道治理;
③、更换弧形工作门及平板检修门,更换弧门启闭机;
④、加固改造上坝及进库公路;
⑤、增设大坝观测设施与自动化控制系统。
工程于__年5月31日开工建设,__年6月底全面竣工,历时13个月,除险加固工程按照设计批准的方案已完成了主要工程,即:完成了大坝前坝坡加固工程;溢洪道加固及下游河道治理工程;完成上坝公路加固工程,包括1.27公里的公路护坡及3.2公里的沥青路面铺设,以及公路桥1座,过洪涵洞6座;完成输水泄洪洞事故门、工作门、启闭设备制安工程;完成大坝自动化监测设备的安装及其它工程等,由于受地方配套资金影响大坝砼防渗墙工程未能完成和坝体渗流水位测量仪未安装,其余主体工程均已按设计要求完成。
该工程共完成投资额915.24万元(不包括待验费20万元),完成主要工程量为:土石方开挖8.39万m3,土石方回填2.02万m3,浆砌石1.16万m3,砼0.15万m3,耗用水泥1782T,钢筋(钢材)40.54T,木材11.26m3,沥青93.70m3,劳动工日5.69个工日。
二、验收条件检查结果:
依据水利部《水利水电建设工程验收规程》的有关规定,该工程按设计要求已完成了主要
工程施工任务,虽然受地方配套资金影响使个别尾工未能完工,但不影响工程正常安全运用。工程投资使用合理,竣工决算已经完成并通过了竣工审计。竣工资料已准备齐全,工程施工质量已通过了__市水利基本建设质监站的质量检验,并出具了《工程质量检验评定报告》,工程质量合格。在工程完工试运行中,工程能正常运行,经济效益和社会效益显著,已具备正式验收条件。